Karen
I'm running some date-sensitive reports (custom built off
SQL from some samples from Microsoft's site) and getting
slightly discrepant data. I have a feeling it's related
to the specific date and time range I am specifying when
running the reports. When resources enter actuals via
project web access, what time of day are those actuals
put down as? The resources only see the date 'june 10'
or whatever as a place to put hours, and they only
indicate total # of hrs for the day. Where does Project
then store those hours? 8 am - 5 pm? Or 12:01 AM - 8
am? or starting at 12:01 am and running until the total
# of hours for the task for that day are entered?
Thanks in advance, this is really throwing me for a loop.
Karen
SQL from some samples from Microsoft's site) and getting
slightly discrepant data. I have a feeling it's related
to the specific date and time range I am specifying when
running the reports. When resources enter actuals via
project web access, what time of day are those actuals
put down as? The resources only see the date 'june 10'
or whatever as a place to put hours, and they only
indicate total # of hrs for the day. Where does Project
then store those hours? 8 am - 5 pm? Or 12:01 AM - 8
am? or starting at 12:01 am and running until the total
# of hours for the task for that day are entered?
Thanks in advance, this is really throwing me for a loop.
Karen