D
djhurayt
We have some tasks that are in our project that all we know (and/or care
about) is that it will take X days for them to complete. How should we treat
this task? We do not want any hours assigned to it because it is hours that
do not have any internal costs associated with them (as far as our department
is concerned). This Engineering Gantt has task in it that other departments
or vendors must perform. If we set it as “fixed duration†with zero hours
and have a resource (department or vendor) assigned to it the Gantt chart bar
does not show up. All we get is a zero hour vertical bar with a tracking
line that starts at the location that would be the end of the task. however
when the task does not have a resource assigned to it the bar shows like a
normal (if there is such a thing in Project) task.
about) is that it will take X days for them to complete. How should we treat
this task? We do not want any hours assigned to it because it is hours that
do not have any internal costs associated with them (as far as our department
is concerned). This Engineering Gantt has task in it that other departments
or vendors must perform. If we set it as “fixed duration†with zero hours
and have a resource (department or vendor) assigned to it the Gantt chart bar
does not show up. All we get is a zero hour vertical bar with a tracking
line that starts at the location that would be the end of the task. however
when the task does not have a resource assigned to it the bar shows like a
normal (if there is such a thing in Project) task.