ks2008 --
When you apply the Task Usage view, you see the complete list of tasks, plus
the the resource assignments for each task. The resource assignments are
the names of the resources assigned to each task. In the default Task Usage
view, you see the Work column to the right of the Task Name column. This
column shows you the total amount of Work for the task, plus the Work for
each resource assignment. When you look at the Work value for any resource
assignment, you are actually looking at the assignment field called Work.
Any column you see in the Task Usage view that has data in it for a resource
assignment is showing you the assignment field information. The same is
true for the Resource Usage view as well. Hope this helps.