Andy Trow said:
Thanks. What about directly linking the end date to the % of a task
completed. eg a 4 week task is only 75% complete therefore I am a week
behind
schedule, or a 4 week task was completed after 2 weeks ? Is the only way
to
actualy change finished date
Andy,
I think you are missing the concept of a dynamically linked schedule. If
a 4 week [duration] task is only 75% complete, that does NOT necessarily
mean the task is a week behind. If the task is only 75% after 4 weeks,
then yes, it is a week behind. But if the task is 75% complete at the
end of 3 weeks, then the task is right on schedule.
Steve suggested working with actual duration and remaining duration
which surprised me because Steve is a effort type of guy. Except in a
very limited number of cases duration doesn't accomplish anything.
Duration is simply the passage of time. Work effort by resources
assigned to the task is where the "rubber hits the road". That is why
the best way to track progress on a task is via % Work Complete. So the
real question to ask is, how many hours of the estimated work content
for a task is actually completed. I suggest you work with the Actual
Work field and the Remaining Work field. As Steve pointed out, doing so
will allow Project to re-calculate your schedule and adjust all dates
accordingly.
John
Project MVP