When does Resource Availability update?

T

Todd

Hi,

When looking at Resource Availability for a user, I may go into Project
Pro and extend some of the deadlines for a resource because they are
over-allocated for a certain day or week. Then I save the project and
re-publish the assignments.

However, when I go back into PWA, the Resource Availability still shows
the over-allocation. When do the resource availability tables get
updated? I have checked Manage Enterprise Features and am using a date
range of Next 6 months to Past 3 months so this doesn't seem to be a
problem.

I guess I'm just wondering when I can expect to see a change in the
Resource availability charts after making changes in Project Pro.

Thanks,
Todd
 
D

Dale Howard [MVP]

Todd --

They get updated as often as you have the system update the OLAP cube data.
Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top