Lamby
I am linking tasks with a finish-to-start dependency.
I have only entered subtask durations, resources, and
predecessors. I know not to touch dates, etc.
Here is what is happening:
For example, task 11 is scheduled to start on Feb 8 and end
on Feb. 24 (it is a 3 wk task).
Task 13 (a 1 week duration task) is dependent on task 12
ending.
I type "12" into the predecessor field of Task 13's record.
The arrows link from the end of task 12 to the beginning of
task 13, but their start dates remain identical - Feb 8.
Task 13 is not shoving out like it is supposed to.
This is happening with some tasks, not all. Some are
shoving out as intended.
I have only entered subtask durations, resources, and
predecessors. I know not to touch dates, etc.
Here is what is happening:
For example, task 11 is scheduled to start on Feb 8 and end
on Feb. 24 (it is a 3 wk task).
Task 13 (a 1 week duration task) is dependent on task 12
ending.
I type "12" into the predecessor field of Task 13's record.
The arrows link from the end of task 12 to the beginning of
task 13, but their start dates remain identical - Feb 8.
Task 13 is not shoving out like it is supposed to.
This is happening with some tasks, not all. Some are
shoving out as intended.