D
DSnyder
Does anyone anywhere know precisely how and when what conditions cause
fixed duration tasks to change duration?
We've had MPS Server 2003 implemented for a couple of years and have
just moved to managed time periods (labor is reported from 80+
resources via PWA).
But even before implementing managed time periods, we were getting
fixed duration tasks that change duration when accepting time. (I can
also get fixed duration tasks to change duration when I manually enter
more remaining work or work - usually when the task is at 100%
complete - this happens even when a finish on constraint is applied).
Now that we are sync-ing time with managed time periods the fixed
duration tasks give up the ghost and float about to some unexplained
algorithm.
What makes it worse is the local expectation that fixed work means
fixed start and finish dates. Basically, the PM's want the duration,
start and finish dates to stay fixed and allow units to soar if needed.
Their intention is to then manage the project through working down
over utilized resources.
Any thoughts, direction, or workaround would be appreciated.
fixed duration tasks to change duration?
We've had MPS Server 2003 implemented for a couple of years and have
just moved to managed time periods (labor is reported from 80+
resources via PWA).
But even before implementing managed time periods, we were getting
fixed duration tasks that change duration when accepting time. (I can
also get fixed duration tasks to change duration when I manually enter
more remaining work or work - usually when the task is at 100%
complete - this happens even when a finish on constraint is applied).
Now that we are sync-ing time with managed time periods the fixed
duration tasks give up the ghost and float about to some unexplained
algorithm.
What makes it worse is the local expectation that fixed work means
fixed start and finish dates. Basically, the PM's want the duration,
start and finish dates to stay fixed and allow units to soar if needed.
Their intention is to then manage the project through working down
over utilized resources.
Any thoughts, direction, or workaround would be appreciated.