Where are actual hours in project database file

J

Joe

I just saved a project as a database file. I want to
query and create a report off of the data found in the
Resource Usage View. Specifically, I want to capture
actual hours by day, which is available on this view, but
I can't find it in the database.
 
B

Brian K - Project MVP

Joe said:
I just saved a project as a database file. I want to
query and create a report off of the data found in the
Resource Usage View. Specifically, I want to capture
actual hours by day, which is available on this view, but
I can't find it in the database.

First off there is a check box that you will want to check on the Tools
| Options dialog on the Save tab. It is called Expand Timephased Data
in the database.

Then look at projdb.htm on either the install CD or on your HD where
you installed Project and the methods for accessing this timephased
data will be explained.

:)
 
J

Joe

Thanks a lot, I REALLY appreciate this info!!!
-----Original Message-----


First off there is a check box that you will want to check on the Tools
| Options dialog on the Save tab. It is called Expand Timephased Data
in the database.

Then look at projdb.htm on either the install CD or on your HD where
you installed Project and the methods for accessing this timephased
data will be explained.

:)

--
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top