Where are the Personal Calendars at?

S

spatton

I am trying to block out individual Resource time for vacations - in
reading a prior post, it talked about doing this on the individual
calendar through the Resoruce Pool. I can find the Resource Pool, but
do not see any individual calendars. Any information on what I am
doing wrong?

We are using MS Project 2007 SP1.

Thanks

Steve
 
B

Ben Howard

Hi Steve,
Open the resource pool in Project Pro, and then for the resource, edit the
details and click on the Change Working Time button in the General tab.
Create a non-working exception as required.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top