Hi Lene,
If you are after vacation time of all resources you will not get past either
Data Analyser or reporting Services. since Project Server 07 has a reporting
db, all resource relevant informtion is stored in this db allowing you to
report against it with a reporting tool like Reporting services.
I dont think it will be feasable or possible to create a vacation report in
Project Pro. The main reason for this is becuase admin tasks are not maintain
in a schedule, they are maintained in Proejct Server hence the reason for
data Analyser or Reporting services.
Hope this helps
--
Marc Soester [MVP]