Where do I specify the RBS level for a resource?

T

Tim Burbage

Hi there...

I just finished setting up my RBS, and Resource Pool, but I seem to be
having one problem. I can't seem to figure out how to specify where in the
RBS each resource should be. I thought it would be in Custom Fields section
of the Resource Information dialogue box, but there is no line item for RBS
there.

Any ideas as to where I can specify this information?

Thanks!

Tim
 
T

Tim Burbage

Thank for your help. I think I was doing something funky originally. I
couldn't add it to the Resource Sheet either. I closed out of Project
completely, and when I went back in, the RBS was where I was expecting it,
and where you suggested I add it.

Thanks!
 
J

JodyJ

FYI - Changes to the Enterprise Global Template are not available until you
exit out of MS Project Pro and re-launch the app.
 