Where is access to the Timesheet and Gantt Chart view defined?

M

Michael

We are using MS Project 2003 with MS Project Web Server.

Within the Tasks area of Project Web, our users are able to "Show tasks
using" either a "Timesheet view" or "Gantt Chart" view.

Can someone tell me where access to these views are defined. I'd like
to temporarily disable the Timesheet view for certain groups of users.
I would however like them to still have access to the Tasks tab with
ability to see the Gamtt Chart view of their tasks.

Thanks in advance.
 
D

Dale Howard [MVP]

Michael --

You cannot disable the Timesheet view on the View my tasks page. If your
organization uses either the Percent Work Complete or Actual Work Done and
Work Remaining method of tracking progress, however, the system will
automatically apply the Gantt Chart view on the View my tasks page for all
users. To prevent them from applying the Timesheet view, you should make
this a training and performance issue with your team members. Hope this
helps.
 