Where is baseline last saved date stored?

G

Greg Horodeck

I am using Project 2002 Professional and Server.

When I create a baseline, the date the baseline was last saved is retained.
When I go into Tools, Tracking, Save Baseline and drop down the basline, it
indicates when the baseline was last saved.

I am looking for where this date, both for the default baseline as well as
for baselines-10 is stored in the database.


Greg Horodeck
 
R

Rod Gill

Hi,

There are separate tables for task, resource and assignment baseline data.
Search your program folders for projdb.htm for full details.

--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
G

Greg Horodeck

Rod,

Thanks and I was aware of these three tables. Unfortunately, the information
I am looking for does not reside in any of these tables. I am looking for
the date that the baseline was created for the project, not the values that
the baseline stores for tasks, resources and assignments.

When you select the dropdown in Project Pro under Tools, Tracking, Save
Baseline, it will tell you the date when a baseline was created, that's the
information I am looking for.


Greg




"Rod Gill" <rodg at project-systems dot co dot nz> wrote in message
Hi,

There are separate tables for task, resource and assignment baseline data.
Search your program folders for projdb.htm for full details.

--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top