R
Rich C
Hi Everyone
Project Server/Project Pro 2003
We have asked our PMs to add fixed costs to their plans. I have set up a new
task outline code with a list of 20 finance cost codes (I have added this
outline code to the Portfolio Analyser using PA Extender) The PM navigates to
a custom cost view in MS Pro, and for each task chooses the appropriate code
from the drop down list and then adds the cost value in the Fixed Cost
column...so far so good.
I went to create a Portfolio Analyser view to show this info but the Fixed
Cost total does not seem to appear in the field list. If I create the view
using the cost total, then any resource costs on the task get shown as well!
is there a way to solve this?. I really need a PA report that shows fixed
costs only.
It seems to be a major flaw, unless I've missed something?
Thanks
Rich
Project Server/Project Pro 2003
We have asked our PMs to add fixed costs to their plans. I have set up a new
task outline code with a list of 20 finance cost codes (I have added this
outline code to the Portfolio Analyser using PA Extender) The PM navigates to
a custom cost view in MS Pro, and for each task chooses the appropriate code
from the drop down list and then adds the cost value in the Fixed Cost
column...so far so good.
I went to create a Portfolio Analyser view to show this info but the Fixed
Cost total does not seem to appear in the field list. If I create the view
using the cost total, then any resource costs on the task get shown as well!
is there a way to solve this?. I really need a PA report that shows fixed
costs only.
It seems to be a major flaw, unless I've missed something?
Thanks
Rich