Where is the Status Manager field in PWA 2007?

R

Robert

Hello,

I'm trying to insert the Status Manager field in a view of PWA (at the task
level in a Project View) but I don't find it!
Could you tell me where is it?
Thanks in advance
 
D

Dale Howard [MVP]

Robert --

Bad news, my friend: this field is not available in PWA. It is only
available in Project Professional 2007 for enterprise projects. Hope this
helps.
 