P
Peters
Hello,
I am searching for some guidance on best practice on using MS Project in
conjunction with MS Project. Doing the WBS and assigning resources and cost
are not a problem. That is described everywhere. But when you go into
tracking, what is the best practice?
Not using Project Server, I would be doing manual updating of actual work.
Should I record remaining hours for every task, or do the not "started,
started, complete" method? And if so, which fields/method are the right ones
to use in MS Project if I want to be able to edit tasks to reflect the
current situation without destroying the base for earned value calculations?
What is the most practical way of exporting data to Excel without having to
do manual editing of the data every time (VBA?)?
I am hoping that there is a guide that someone could recommend with
practical advice that would cover areas such as the ones I have mentioned
above?
Thanks in advance,
Peters
I am searching for some guidance on best practice on using MS Project in
conjunction with MS Project. Doing the WBS and assigning resources and cost
are not a problem. That is described everywhere. But when you go into
tracking, what is the best practice?
Not using Project Server, I would be doing manual updating of actual work.
Should I record remaining hours for every task, or do the not "started,
started, complete" method? And if so, which fields/method are the right ones
to use in MS Project if I want to be able to edit tasks to reflect the
current situation without destroying the base for earned value calculations?
What is the most practical way of exporting data to Excel without having to
do manual editing of the data every time (VBA?)?
I am hoping that there is a guide that someone could recommend with
practical advice that would cover areas such as the ones I have mentioned
above?
Thanks in advance,
Peters