B
Burnley81
I have plenty of project plans - and one I have if basically a odd jobs plan.
I have tasks in there where most are scheduled - a few though have no dates
- everything else is complete for these tasks, resource, duration etc.
Currently they sit at the start of the plan - dated 01/01/09.
Unfortunately the resource usage shows them as being over allocated in work
on this day. I cannot have this as the Master Plan must not show over
allocation.
The only way I can find at present to overcome this is reduce the duration
to "0" and put notes in the Task Allocation for the real duration - so that I
can update when it does come to scheduling this work.
Is there an easier way of not scheduling work - and not affecting resource
allocation?
Thanks
I have tasks in there where most are scheduled - a few though have no dates
- everything else is complete for these tasks, resource, duration etc.
Currently they sit at the start of the plan - dated 01/01/09.
Unfortunately the resource usage shows them as being over allocated in work
on this day. I cannot have this as the Master Plan must not show over
allocation.
The only way I can find at present to overcome this is reduce the duration
to "0" and put notes in the Task Allocation for the real duration - so that I
can update when it does come to scheduling this work.
Is there an easier way of not scheduling work - and not affecting resource
allocation?
Thanks