R
Rich C
Hi Everyone
MSP2003
Project Server 2003...
I am trying to run an automated report using tables from the project
database. Specifically, I am trying to extract Enterprise Outline Task Code
information but am unsure where the data is stored.
Example: This morning I created a new Enterprise Outline Task Code (Code 6)
in the Global file, populated the look-up table with some values, and then
saved the global file. Then I created a new project plan and assigned one of
the values from the new code to some of the tasks. I then published the plan.
I reopened the plan to check that the outline code values had been saved,
which they had.
The OLAP cube hasn't run yet so the MSP_CUBE_ENTERPRISE_TASK_OUTLINE_6 table
has no data in it. So in summary, where is the task outline code value stored
when the project plan is published?
Thanks
MSP2003
Project Server 2003...
I am trying to run an automated report using tables from the project
database. Specifically, I am trying to extract Enterprise Outline Task Code
information but am unsure where the data is stored.
Example: This morning I created a new Enterprise Outline Task Code (Code 6)
in the Global file, populated the look-up table with some values, and then
saved the global file. Then I created a new project plan and assigned one of
the values from the new code to some of the tasks. I then published the plan.
I reopened the plan to check that the outline code values had been saved,
which they had.
The OLAP cube hasn't run yet so the MSP_CUBE_ENTERPRISE_TASK_OUTLINE_6 table
has no data in it. So in summary, where is the task outline code value stored
when the project plan is published?
Thanks