A
anovak
Assuming Fixed Units and Non-Effort Driven...
1. Enter estimated work hours, make assignment and let MS Project
schedule the duration and calculate the dates based on resource
availability.
2. Enter estimated Duration and let MS Project calculate the dates
(benefit is to see the dates before a "real" assignment is made), then
make assignment and let MS Project calculate estimated work hours
during that duration based on resource availability (if two half time
people are assigned to a 5 day task, then the total work hours would
be 40).
I've been preaching #1 for quite a while, but I'm beginning to thing
that #2 is easier for the users and more manageable.
Thanks,
Andy Novak
UNT
1. Enter estimated work hours, make assignment and let MS Project
schedule the duration and calculate the dates based on resource
availability.
2. Enter estimated Duration and let MS Project calculate the dates
(benefit is to see the dates before a "real" assignment is made), then
make assignment and let MS Project calculate estimated work hours
during that duration based on resource availability (if two half time
people are assigned to a 5 day task, then the total work hours would
be 40).
I've been preaching #1 for quite a while, but I'm beginning to thing
that #2 is easier for the users and more manageable.
Thanks,
Andy Novak
UNT