H
hooploid
When you are tracing through a schedule, is there an easy way to find out
which predecessor drives the start date of the task you are on?
I constantly find myself looking at a task which is not on the critical
path, and which has lots of predecessors, wondering which one is driving the
start date. What I do now is go to each of those predecessors and compare
finish dates to my task's start date. But there must be an easier way. It's
too bad Project doesn't just highlight it on the list of pred/successors in
the bottom pane--is there some feature I don't know about?
which predecessor drives the start date of the task you are on?
I constantly find myself looking at a task which is not on the critical
path, and which has lots of predecessors, wondering which one is driving the
start date. What I do now is go to each of those predecessors and compare
finish dates to my task's start date. But there must be an easier way. It's
too bad Project doesn't just highlight it on the list of pred/successors in
the bottom pane--is there some feature I don't know about?