Hi,
I am using PS2007, SP1
People are used to add text when updating tasks progress within PWA:
- text is visible within "Comments" column of the My Tasks view before PUBLISH
- then added within "notes" field each time tasks progress have been
approved and RE-PUBLISHED.
I'd like to issue following report:
display "Comments" and/or "Notes" fields for all tasks of a given resource
(on a given period of time).
What is best way to obtain such report?
Thanks in advance
jpa
I am using PS2007, SP1
People are used to add text when updating tasks progress within PWA:
- text is visible within "Comments" column of the My Tasks view before PUBLISH
- then added within "notes" field each time tasks progress have been
approved and RE-PUBLISHED.
I'd like to issue following report:
display "Comments" and/or "Notes" fields for all tasks of a given resource
(on a given period of time).
What is best way to obtain such report?