I am interested in reporting on timephased Baseline Work Hours.

I currently use the MSP_Cube_Assn_Fact table for my static, daily reports.
My understanding is that this table gets updated when the nightly OLAP Cube
is run.

Which table contains similar data in real-time (not dependent on Cube).
I've looked at all the MSP_ xxx tables but either can't find it or am unable
to interpret the table. I will need both Baseline Work and Actual Work in
the table.

Thanks in advance for your time.
 
G

Gaurav Wason

"AssignmentTimeBaselineWork" is field and table is
"msp_view_proj_assn_tp_by_day"

**Remember this table will only have the information if the project is
published.