C
Conrad Santiago
I have a few questions on task ownership:
1. If Bob is the Owner of the project and Jim opens up the project and adds
a task, assigning it to Mary, then publishes the assignment, who is the
manager of the task?
2. If Jim is the manager of a task, then later Bob opens up the project and
changes the assignment to Sally, then publishes the assignment change, who
then is the manager of the task?
3. What if Jim creates the task, then assigns it to a generic resource
instead of a specific resource. Will this make a difference on who ends up
as manager of the task?
The reason I ask these questions is that we are using the Updates feature in
PWA and I want to understand what would cause Updates to go to someone other
than the Owner of the project.
1. If Bob is the Owner of the project and Jim opens up the project and adds
a task, assigning it to Mary, then publishes the assignment, who is the
manager of the task?
2. If Jim is the manager of a task, then later Bob opens up the project and
changes the assignment to Sally, then publishes the assignment change, who
then is the manager of the task?
3. What if Jim creates the task, then assigns it to a generic resource
instead of a specific resource. Will this make a difference on who ends up
as manager of the task?
The reason I ask these questions is that we are using the Updates feature in
PWA and I want to understand what would cause Updates to go to someone other
than the Owner of the project.