K
Kevin Newman
Let me preface this by saying that we just got Project Server up and running
for the first time yesterday. We are now in the process of defining resources
and security levels (among other things).
We are a repair facility with about 200 employees, many of which have
disparate qualification levels. We were thinking that we could have each of
those individuals record their time against activities using the PWA
timesheet, but now that I have had a day to play with it I have come to the
conclusion that only Team Members can record their time that way. Am I right?
Am I going to have to assign each individual as a resource, and then as a
Team Member in order to make this work? This is really a cumbersome process
due to the disparate skill levels within our organization.
Any solutions? Am I going to have to build a custom interface to allow
individuals to record their time and then use that to update Project Server?
Thanks in advance
Kevin
for the first time yesterday. We are now in the process of defining resources
and security levels (among other things).
We are a repair facility with about 200 employees, many of which have
disparate qualification levels. We were thinking that we could have each of
those individuals record their time against activities using the PWA
timesheet, but now that I have had a day to play with it I have come to the
conclusion that only Team Members can record their time that way. Am I right?
Am I going to have to assign each individual as a resource, and then as a
Team Member in order to make this work? This is really a cumbersome process
due to the disparate skill levels within our organization.
Any solutions? Am I going to have to build a custom interface to allow
individuals to record their time and then use that to update Project Server?
Thanks in advance
Kevin