KatiefromAurora
I'm working in Project 2003 and when I run a Who Does What report in one
subproject for one resource, it pulls data from all subprojects connected to
the master. The problem is, when this other data appears, it shows the
resource as always having 100% units. That doesn't make sense. For
instance, the resource I ran the report for is working 7 hours over a month.
That would not equal 100% of their units. Can anyone tell me why the correct
percentage is not showing up?