I would like to create a report for each of the guys working on my project
that shows:
1) their tasks,
2) when they need to finish each task
3) how many hours I think each task should take.
This will help them plan their workload.
The closest report is the "Who Does What" report - but there are aspects of
the report I don't like.
1) (most important), it doesn't put the tasks in order by date. I have tried
to "sort by finish" in the "sort" tab, but it doesn't have any effect on the
report.
2) it has too many columns - can I hide some of the columns?
3) I want one report for each person - not a combined report - how can I do
that?
So perhaps there is a completely different, creative way I can get at the
data I want.
Suggestions anyone?
Thanks,
Judy
that shows:
1) their tasks,
2) when they need to finish each task
3) how many hours I think each task should take.
This will help them plan their workload.
The closest report is the "Who Does What" report - but there are aspects of
the report I don't like.
1) (most important), it doesn't put the tasks in order by date. I have tried
to "sort by finish" in the "sort" tab, but it doesn't have any effect on the
report.
2) it has too many columns - can I hide some of the columns?
3) I want one report for each person - not a combined report - how can I do
that?
So perhaps there is a completely different, creative way I can get at the
data I want.
Suggestions anyone?
Thanks,
Judy