Who Does What Report

B

brighousej

Hi, Ive run the 'Who Does What' report but it is not listing tasks in I
order. For example, Mr A has 100 tasks allocated to him, but task 50 i
appearing in the report before task 25, even though task 25 is takin
place earlier. I can't see any logic as to why tasks may be listed thi
way. Can anyone help
 
J

John

brighousej said:
Hi, Ive run the 'Who Does What' report but it is not listing tasks in ID
order. For example, Mr A has 100 tasks allocated to him, but task 50 is
appearing in the report before task 25, even though task 25 is taking
place earlier. I can't see any logic as to why tasks may be listed this
way. Can anyone help?

brighousej,
I wouldn't swear by this but I believe Project sets the sequence in the
order in which the resource is assigned. For example, if Mr. A was
assigned to task 50 before he was assigned to task 25, the assignments
stay in that order.

If the time sequence is important to you, you could use the Resource
Usage view and then sort on the Start field.

John