Hi ks2008,

There is no automatic way to run the report and return only a
selected resource.

In quick testing I created a simple resource filter which prompts to
enter a resource name. It appears to work fine on the Resource
Usage view, however on both Project 2003 and Project 2007, when
applied to the "Who Does What When Report" it hides the detail of
the assignments. My recommendation is to filter the Resource Usage
view, and print the view if you wish to only show one resource at a
time.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
J

JulieS

You're welcome KS and thanks for the feedback.

As to the techarena forum -- yes, the posts appear there as well
because techarena is displaying posts from this newsgroup hosted by
Microsoft.
Julie
 