J
Jiaheng Qin
The question is:
I've finished look up table of RBS in PWA 2007 and assigned the resourses
the level within RBS.
General manager Resource A
Vice GM Resource B
Dept. Manager Resource C
Vice D.M. Resource D
Clerk Resource E
General Manager creates a whole new project, define tasks, creates
workgroup, then assign task to above-mentioned resources. He saved and
published project to server.
According to logical thinking that Resource E automatically report to
Resource D, D report to C, C to B and B to A.
But in the system, I can't see any function of RBS.
Who can give me an explanation about how RBS works in EPM 2007 and what is
the procedure on setting up details.
I'm mad during several moths work, but it seems that there is still no answer.
Thank you all.
Best regards
Jiaheng Qin
I've finished look up table of RBS in PWA 2007 and assigned the resourses
the level within RBS.
General manager Resource A
Vice GM Resource B
Dept. Manager Resource C
Vice D.M. Resource D
Clerk Resource E
General Manager creates a whole new project, define tasks, creates
workgroup, then assign task to above-mentioned resources. He saved and
published project to server.
According to logical thinking that Resource E automatically report to
Resource D, D report to C, C to B and B to A.
But in the system, I can't see any function of RBS.
Who can give me an explanation about how RBS works in EPM 2007 and what is
the procedure on setting up details.
I'm mad during several moths work, but it seems that there is still no answer.
Thank you all.
Best regards
Jiaheng Qin