Who updated a project

B

Burnley81

I have with reasonable results set-up a resource pool and a master plan for 3
divisions of a company.
Project plans are available to all - the Project Managers are wary that
their plans may be altered without their knowledge. Is there a way to find
out who last updated a project file or even better a specific part of a
project?
Thanks Andy
 
M

Mike Glen

Hi Burnley,

There's no way to do this in Project standard. You must insist on the
discipline laid down in your company policy (you do have one don't you?)
If, however, you're using a server, try posting on the
microsoft.public.project.server newsgroup (forum). Please see FAQ Item: 24.
Project Newsgroups. FAQs, companion products and other useful Project
information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top