Hi Meg,
Pardon me for bumping in -- is it possible the milestones are just
far left in the timescale and not currently in your view? When
adding new tasks, by default they are placed back at the start date
of the project until you create the task relationships. If you
click on the newly added task in the list and click the Go To
Selected task button, are they now in view?
I hope this helps. Let us know how you get along.
Julie
Project MVP