P
pmwashtwpnj
When I put in work, actual work, and remaining work hours, project calculates
incorrectly for main header task. For example, I have a heading,
sub-heading, then task list. I have work hours entered for the task list,
and the sub-heading calculates correctly. However, the main header
calculates way too many hours (for example I have manually put in 14 hours of
actuals, and the main heading says there are 74...sub heading says the
correct 14 hours), and can be manipulated by changing start and finish dates.
I don't want start and finish dates to affect ANY work numbers. I only want
dates as references, not as active parts of the project. I only care about
work, actual work, and estimated work to complete.
incorrectly for main header task. For example, I have a heading,
sub-heading, then task list. I have work hours entered for the task list,
and the sub-heading calculates correctly. However, the main header
calculates way too many hours (for example I have manually put in 14 hours of
actuals, and the main heading says there are 74...sub heading says the
correct 14 hours), and can be manipulated by changing start and finish dates.
I don't want start and finish dates to affect ANY work numbers. I only want
dates as references, not as active parts of the project. I only care about
work, actual work, and estimated work to complete.