Why do I have a schedule that thinks 5 days is Monday to Monday?

E

Elle

....and another that thinks 5 days is Monday to Friday?

How do I correct the one that knows 5 days is just Monday to Friday? or
Tuesday to Monday etc

Thanks
 
J

JulieS

Hello Elle,

First I suggest checking what time the Monday to Monday task starts.
If you are not showing the time and date, go to Tools > Options,
View tab and change the date format. A task that doesn't start at
the beginning of your work day on Monday and has a 5 day duration
will end on the following Monday.

Start there and let us know how you get along.

I hope this helps.

Julie
Project MVP
 