David
I can't seem to get summary taks to display correct durations, and yes, I
know it's supposed to be from the start date of the first task to the end
date of the last task. Here's an example from adding a recurring task
(Monday update meeting) to a project. The span is 35 days. The summary task
shows a duration of 105.13 days.
Remodel Status Meeting 105.13d Mon 4/21/08 Mon 5/26/08
Remodel Status Meeting 1 1h Mon 4/21/08 Mon 4/21/08
Remodel Status Meeting 2 1h Mon 4/28/08 Mon 4/28/08
Remodel Status Meeting 3 1h Mon 5/5/08 Mon 5/5/08
Remodel Status Meeting 4 1h Mon 5/12/08 Mon 5/12/08
Remodel Status Meeting 5 1h Mon 5/19/08 Mon 5/19/08
Remodel Status Meeting 6 1h Mon 5/26/08 Mon 5/26/08
Another summary task in a different project shows a duration of 0.38 days
for 6 tasks totaling 16 hours of fixed work for one person working a standard
calendar and work week. The resource is otherwise unassigned. The work column
totals correctly, just not the summary task duration.
Wed 1/2/08 0.38d Fixed Duration 16h
Wed 1/2/08 3h Fixed Work 3h
Wed 1/2/08 3h Fixed Work 3h
Wed 1/2/08 3h Fixed Work 2h
Wed 1/2/08 3h Fixed Work 3h
Wed 1/2/08 2h Fixed Work 2h
Wed 1/2/08 3h Fixed Work 3h
Thanks for any advice you can offer.
know it's supposed to be from the start date of the first task to the end
date of the last task. Here's an example from adding a recurring task
(Monday update meeting) to a project. The span is 35 days. The summary task
shows a duration of 105.13 days.
Remodel Status Meeting 105.13d Mon 4/21/08 Mon 5/26/08
Remodel Status Meeting 1 1h Mon 4/21/08 Mon 4/21/08
Remodel Status Meeting 2 1h Mon 4/28/08 Mon 4/28/08
Remodel Status Meeting 3 1h Mon 5/5/08 Mon 5/5/08
Remodel Status Meeting 4 1h Mon 5/12/08 Mon 5/12/08
Remodel Status Meeting 5 1h Mon 5/19/08 Mon 5/19/08
Remodel Status Meeting 6 1h Mon 5/26/08 Mon 5/26/08
Another summary task in a different project shows a duration of 0.38 days
for 6 tasks totaling 16 hours of fixed work for one person working a standard
calendar and work week. The resource is otherwise unassigned. The work column
totals correctly, just not the summary task duration.
Wed 1/2/08 0.38d Fixed Duration 16h
Wed 1/2/08 3h Fixed Work 3h
Wed 1/2/08 3h Fixed Work 3h
Wed 1/2/08 3h Fixed Work 2h
Wed 1/2/08 3h Fixed Work 3h
Wed 1/2/08 2h Fixed Work 2h
Wed 1/2/08 3h Fixed Work 3h
Thanks for any advice you can offer.