MS Project 2007. Tasks with scheduled start dates in the past but not yet
started are not being pushed to the current date. Project 2003 would do this
but I have been unable to get Project 2007 to work. I want a string of
linked tasks scheduled to start in the past to show the dates they could
actually start/finish based on the current date.
 
J

JulieS

Hello AMED,

You need to use Tools > Tracking > Update Project > Reschedule
uncompleted work to push the incomplete tasks to start on the current
date or status date.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information