Why do Work hours increase

G

Gail

In my project, I have a task with a baseline of 40 work hours and a task type
of Fixed Units. I have been doing some updates - only updating the Actual
Work for tasks previous to this task. Now this task has 1098.83 work hours.
Can anyone explain why?
 
M

Marc Soester [MVP]

Gail, the only reason why work would increase is if your actual work has
1098.83 work or the accumulation of actual and remaining work = to 1098.93
The only other reason why this could happen is if your schedule is corrupt :(
hope this helps
 
G

Gail

How does a project get corrupted?

Marc Soester said:
Gail, the only reason why work would increase is if your actual work has
1098.83 work or the accumulation of actual and remaining work = to 1098.93
The only other reason why this could happen is if your schedule is corrupt :(
hope this helps
 
G

Gail

We have installed the infrastructure update and some hotfixes. I will close
this for now until I see if it contines.
 
G

Gary L. Chefetz

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top