K
kraus
I work in a small organization that shares resources across different
projects. To manage this we utilize the leveling functionality to ensure we
don't have resources overallocated.
What I have seen is that my resource, allocated at 70%, is scheduled for
1.45 days of work. The other project has since added the same resource,
allocated at 80%, for the same week and levelled. As a result, when I go into
my plan and level first thing my 1.45 days scheduled has reduced to 1.4 days.
This then waterfalls on until the .05 of a day can find a home, which
depending on the resources allocation on other projects could push out a long
time.
It is my understanding that once a resource is allocated and levelled
against the organization then that resource is "spoken for". All other
projects that require the same resource would then be forced to work around
the time frame that my project requires the resource. It doesn't appear to be
happenning in this instance. Any suggestions?Neither plan has set any
priority specific work (if it helps)
Thx
projects. To manage this we utilize the leveling functionality to ensure we
don't have resources overallocated.
What I have seen is that my resource, allocated at 70%, is scheduled for
1.45 days of work. The other project has since added the same resource,
allocated at 80%, for the same week and levelled. As a result, when I go into
my plan and level first thing my 1.45 days scheduled has reduced to 1.4 days.
This then waterfalls on until the .05 of a day can find a home, which
depending on the resources allocation on other projects could push out a long
time.
It is my understanding that once a resource is allocated and levelled
against the organization then that resource is "spoken for". All other
projects that require the same resource would then be forced to work around
the time frame that my project requires the resource. It doesn't appear to be
happenning in this instance. Any suggestions?Neither plan has set any
priority specific work (if it helps)
Thx