A
anovak
I'm attempting to utilize the budget cost capability by assigning a
project budget at the project level, defining multiple expense
resources and assigning them to a task called "Procurement".
When in the Resource Usage view, I split the screen in order to enter
the Cost amount in a particular FY or month within the FY. If a
Server costs $4,000 and I enter that amount in a particular FY or
month within the year, often times it enters other odd amounts in
subsequent FY/months, and changes the figure I entered.
I even went back to the Procurement task to ensure that the start and
end dates spread across the entire time (both FY) w/fixed duration.
What in the heck is going on? I need to demo this to Mgt very
shortly and this does not look good.
Please advise. Perhaps there's just a little bit I need to flip
somewhere.
Thanks,
Andy Novak
UNT
project budget at the project level, defining multiple expense
resources and assigning them to a task called "Procurement".
When in the Resource Usage view, I split the screen in order to enter
the Cost amount in a particular FY or month within the FY. If a
Server costs $4,000 and I enter that amount in a particular FY or
month within the year, often times it enters other odd amounts in
subsequent FY/months, and changes the figure I entered.
I even went back to the Procurement task to ensure that the start and
end dates spread across the entire time (both FY) w/fixed duration.
What in the heck is going on? I need to demo this to Mgt very
shortly and this does not look good.
Please advise. Perhaps there's just a little bit I need to flip
somewhere.
Thanks,
Andy Novak
UNT