StaceyMG
This problem is happening even with a fresh project.
I create 2 tasks, task A and task B. Automatically they both start with
today's date.
Link the tasks so that task B has A as the predecessor with a
Finish-to-Start link.
Set the duration of task A to 5d.
I would expect that this would change task B's start date to 5d later. It
isn't. The link on the Gantt chart indicates a FS start, even though it looks
like they both are starting today.
What am I doing wrong?
I want Project to automatically update task B's start date.
I create 2 tasks, task A and task B. Automatically they both start with
today's date.
Link the tasks so that task B has A as the predecessor with a
Finish-to-Start link.
Set the duration of task A to 5d.
I would expect that this would change task B's start date to 5d later. It
isn't. The link on the Gantt chart indicates a FS start, even though it looks
like they both are starting today.
What am I doing wrong?
I want Project to automatically update task B's start date.