S
Stevie
Hi all,
Since I didn't get very much of an answer to my previous post, I opted
reposting it again here.
What I need is a field to calculate the SPI.
This is how I do it:
I save my baseline, and then afterwards construct my project adding
tasks.
I make the BCWS and BCWP fields show. The strange things begin right
here: the values show zeros.
I afterwards add a field (Number 11 e.g.). I customize it (Tools >
Customize), and configure it so I can add a formula. The formula for
SPI is BCWS/BCWP, and I make it be put in. Still, the value shows a
zero.
I am not very experienced with Project 2000, and I couldn't get it to
workby the explanation of Project help itself.
What I need is a very clear explanation what I should look at.
My configuration is Project 2000 in a Win NT 4.0. environment.
Thanks in advance for your help.
Since I didn't get very much of an answer to my previous post, I opted
reposting it again here.
What I need is a field to calculate the SPI.
This is how I do it:
I save my baseline, and then afterwards construct my project adding
tasks.
I make the BCWS and BCWP fields show. The strange things begin right
here: the values show zeros.
I afterwards add a field (Number 11 e.g.). I customize it (Tools >
Customize), and configure it so I can add a formula. The formula for
SPI is BCWS/BCWP, and I make it be put in. Still, the value shows a
zero.
I am not very experienced with Project 2000, and I couldn't get it to
workby the explanation of Project help itself.
What I need is a very clear explanation what I should look at.
My configuration is Project 2000 in a Win NT 4.0. environment.
Thanks in advance for your help.