A
Ameesh Oza
I have a problem that Microsoft Project changes the duration by -1 day. The
start and finish dates are being updated using VB macros by a 3rd party
application. If original duration was 3 days it becomes 2 days. The
application is not changing the duration in any way - only start and finish
dates. The dates coming from the application are the same as the original
planned start/finish dates. The only difference is that application marks
task as 100% complete. What gives??
thanks
Newbie Ameesh
start and finish dates are being updated using VB macros by a 3rd party
application. If original duration was 3 days it becomes 2 days. The
application is not changing the duration in any way - only start and finish
dates. The dates coming from the application are the same as the original
planned start/finish dates. The only difference is that application marks
task as 100% complete. What gives??
thanks
Newbie Ameesh