C
Carolyn
My schedule is Fixed Duration and I have assigned resources at 75% which
defaults the estimated work to 6 hours per day. I've baselined. Now I want
to enter the actual Start and Finish dates and the actual hours worked and
have Project calculate what the actual allocation to the task was. Here is
an example:
Task Name : 1 day duration : John assigned at 100% : estimated work 8 hours.
1. I enter the start and finish dates which show John actually took 2 days
to do this task.
2. I enter the actual work he reported which was 8 hours
Expected outcome: the resource allocation (100%) will adjust to 50%.
Actual outcome: the resource allocation will not change and I must choose
between reporting the work accurately (8 hrs) and letting MSProject assign an
incorrect duration (1 day) or I may enter the actual duration (2 days) and
let Project assign an incorrect actual work (16 hours).
I tried resetting the Type to Fixed Work, but still got the same result. I
also tried setting the Type to Fixed Units, but still got the same result.
Is there a setting somewhere that I don't know about that is fixing the
resource allocations?
defaults the estimated work to 6 hours per day. I've baselined. Now I want
to enter the actual Start and Finish dates and the actual hours worked and
have Project calculate what the actual allocation to the task was. Here is
an example:
Task Name : 1 day duration : John assigned at 100% : estimated work 8 hours.
1. I enter the start and finish dates which show John actually took 2 days
to do this task.
2. I enter the actual work he reported which was 8 hours
Expected outcome: the resource allocation (100%) will adjust to 50%.
Actual outcome: the resource allocation will not change and I must choose
between reporting the work accurately (8 hrs) and letting MSProject assign an
incorrect duration (1 day) or I may enter the actual duration (2 days) and
let Project assign an incorrect actual work (16 hours).
I tried resetting the Type to Fixed Work, but still got the same result. I
also tried setting the Type to Fixed Units, but still got the same result.
Is there a setting somewhere that I don't know about that is fixing the
resource allocations?