Why dosent total hrs & breakup of recurring task match in Project?

G

gmanand

I have set recurring task as 3 Hrs every workday (Mon - Fri) for 3 months. I
have also set work timings as 8.5 hrs per day. Now in the breakup of the
recurring task I can see 3hrs per day but in the total duration Project
calculates Workdays X 8.5 hrs (thus ignoring the 3hrs that have been given)
 
J

Jan De Messemaeker

Hi,

What you are seeing is duration (the difference between Start and Finish).
If you assign (a) resource(s) to the individual tasks, you can show a column
callend Work; that one will total up as you expect.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
gmanand said:
I have set recurring task as 3 Hrs every workday (Mon - Fri) for 3 months. I
have also set work timings as 8.5 hrs per day. Now in the breakup of the
recurring task I can see 3hrs per day but in the total duration Project
calculates Workdays X 8.5 hrs (thus ignoring the 3hrs that have been
given)
 