T
Tim Garvey
For the weeks of 1/24 and 1/31, whatever hours I schedule (enter in the
"work" cell in the Resource Usage View) for the Project Management task also
appear in the "actual" cell. So I have 27 hours scheduled and actual for
this week and the week after. This doesn't happen for this task for any of
the subsequent weeks beyond 1/31 and going out to August of 2010. It also
doesn't happen for all tasks in my plan, though I can identify 6 or so that
it does happen for.
Any help would be appreciated.
Tim
"work" cell in the Resource Usage View) for the Project Management task also
appear in the "actual" cell. So I have 27 hours scheduled and actual for
this week and the week after. This doesn't happen for this task for any of
the subsequent weeks beyond 1/31 and going out to August of 2010. It also
doesn't happen for all tasks in my plan, though I can identify 6 or so that
it does happen for.
Any help would be appreciated.
Tim