K
KingKikapu
I would like to place a material resource on a 0 Day milestone. Th
material resource (used instead of Cost Resource for EV purposes) merel
represents a contract payout term for achieving the milestone. If the
are late, they start to incurr penalties, so this is by no means a fixe
price cost
I have often heard that it is poor practice to place a resource on
milestone. Could somebody elaborate as to why and under wha
circumstances this is believed to be true? Should I not plan my projec
in the manner described above
Thank you
material resource (used instead of Cost Resource for EV purposes) merel
represents a contract payout term for achieving the milestone. If the
are late, they start to incurr penalties, so this is by no means a fixe
price cost
I have often heard that it is poor practice to place a resource on
milestone. Could somebody elaborate as to why and under wha
circumstances this is believed to be true? Should I not plan my projec
in the manner described above
Thank you