Why is there no way to update timephased costs for a cost resource

T

tfz

Why is there no way to update timephased costs for a cost resource in the
PSI? You can update the timephased work for a work resource, but not the
costs for a cost resource? That seems very inconsistent. Am I just missing
something --is there actually a way to do this?

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...a4a2b02&dg=microsoft.public.project.developer
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top