K
kix1956
Initally I have resource A allocated to two projects. I have task 1 in
plan A assigned to resource A, with work remaining of 2hrs, scheduled
for today. Task 5 in plan B assigned to resource A with work remaining
of 8 hrs scheduled for today results in an overallocation of resource
A, given a standard 8 hr. work day. I open both projects and level
resource A. Now Resource A is scheduled to only work 2 hrs today after
completing task 1, and scheduled to work 8 hrs the next business day
to complete task 5. Okay, so what I want to do is allocate 6hrs of
work for task 5 to today and have resource A complete task 5 the next
business day, completeing the remaining 2 hrs of work. I attempt to
enter 6hrs into the WORK cell for today for task 5 and when I enter
the value, the work remaining is decremented by 6hrs. Given this is
not the Actual work, I would anticipate that if anything Work
remaining would increase by 6hrs, until I subtract the 6hrs from the 8
hrs originally shceduled for the next business day after leveling.
What am I missing?
plan A assigned to resource A, with work remaining of 2hrs, scheduled
for today. Task 5 in plan B assigned to resource A with work remaining
of 8 hrs scheduled for today results in an overallocation of resource
A, given a standard 8 hr. work day. I open both projects and level
resource A. Now Resource A is scheduled to only work 2 hrs today after
completing task 1, and scheduled to work 8 hrs the next business day
to complete task 5. Okay, so what I want to do is allocate 6hrs of
work for task 5 to today and have resource A complete task 5 the next
business day, completeing the remaining 2 hrs of work. I attempt to
enter 6hrs into the WORK cell for today for task 5 and when I enter
the value, the work remaining is decremented by 6hrs. Given this is
not the Actual work, I would anticipate that if anything Work
remaining would increase by 6hrs, until I subtract the 6hrs from the 8
hrs originally shceduled for the next business day after leveling.
What am I missing?