M
ma.u
Hi,
I set physical progress for a task updating
MSP_TASKS.TASK_PHY_PCT_COMP field. Project documentation says that it
should recalculate MSP_TASKS.TASK_BCWP;
but it doesn't work. Why?
(DB is Sql Server 2000, MS Project version is 2003)
I use MSP_BACKUP_TASK on the modified task and set PROJ_EXT_EDITED =
'1'
Thanks.
I set physical progress for a task updating
MSP_TASKS.TASK_PHY_PCT_COMP field. Project documentation says that it
should recalculate MSP_TASKS.TASK_BCWP;
but it doesn't work. Why?
(DB is Sql Server 2000, MS Project version is 2003)
I use MSP_BACKUP_TASK on the modified task and set PROJ_EXT_EDITED =
'1'
Thanks.