Why the duration is changed into tasks when add resources ?

S

Sam

when the project manager open the project in project professional and add
different resources into tasks then the project duration is changed at once.

why it is happening ?
 
R

Rod Gill

You have effort driven on. Effort driven means that when an extra resource
is assigned, all resource share the original wok, so duration reduces. With
effort driven off this does not happen.

Click Windows. Split and the Effort Driven flag can be seen. Under Tools,
Options you can set effort driven off as a default.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Sam said:
when the project manager open the project in project professional and add
different resources into tasks then the project duration is changed at
once.

why it is happening ?

__________ Information from ESET Smart Security, version of virus
signature database 4963 (20100321) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4963 (20100321) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top