Hi all
We are working with project server 2007 SP2
I have a resource that has 3 tasks
His project manager plan for him 3 tasks for 2 month
On the first tasks he was planned with 35% units
On the second task he was planned with 25% units
On the third task he was planned with 40% units
The resource updates his progress via the PWA reporting his actual work.
His status manager approves the updates via the PWA.
When opening the project plan via the project professional the units you can
see that the units next to the resource name have been changed.
We are working with fixed units.
How can I avoid this unit’s change?
Why it is happening?
Best regards
Erez
We are working with project server 2007 SP2
I have a resource that has 3 tasks
His project manager plan for him 3 tasks for 2 month
On the first tasks he was planned with 35% units
On the second task he was planned with 25% units
On the third task he was planned with 40% units
The resource updates his progress via the PWA reporting his actual work.
His status manager approves the updates via the PWA.
When opening the project plan via the project professional the units you can
see that the units next to the resource name have been changed.
We are working with fixed units.
How can I avoid this unit’s change?
Why it is happening?
Best regards
Erez